Transfix Transformers SA
Quality

Quality you can verify

In this industry a failure is not an inconvenience, it is an outage. Every claim Transfix makes about quality is one that can be checked by a third party.

Quality system
SABS ISO 9001
Product
SABS approved
Supplier status
Approved Eskom vendor
Local content
Proudly South African
The oil treatment and vacuum filling plant at the Transfix factory, Botshabelo
Oil treatment, Botshabelo

The oil is tested before it goes in

Dielectric strength, moisture and acidity are measured on every unit as part of the routine test schedule. Oil is then introduced under vacuum, so no air is left in the windings.

Transformation01 / 04

Level 1, one hundred percent black owned

Transfix is a Level 1 contributor and an empowering supplier, which carries 135 percent procurement recognition for the businesses that buy from us.

The company was registered in 2008 and has been in South African hands since E’tsho Holdings acquired a majority stake on 1 January 2017.

Read our story
B-BBEE contributor level
Level 1
Black shareholding
100%
Procurement recognition
135%
Empowering supplier
Yes
Testing02 / 04

Every unit is tested

No transformer leaves Botshabelo untested. Routine production tests are carried out on every unit before dispatch. Type tests verify the design itself, and diagnostic tests are run where a customer or our own quality process calls for them.

Routine production tests, every unit
Winding resistancePoor connections, loose joints, damaged conductors
Insulation resistanceInsulation health, moisture and contamination
Turns ratioWinding ratio and correct tap connections
Polarity and vector groupCorrect connections and specified group, e.g. Dyn11
No load loss and currentCore condition and losses against specified limits
Load loss and impedanceWinding losses and impedance against design
Applied voltage withstandMain insulation against power frequency test voltage
Induced voltageInter turn and inter layer insulation weaknesses
Oil dielectric, moisture, acidityElectrical strength and condition of the oil
Leak, pressure and vacuumTank, radiators, valves and seals
Tap changer and bushingsOperation through tap positions, bushing integrity
Earth continuitySafe connection of exposed metallic parts
Dimensional and visualConformance to approved drawings and specification
Rating plate verificationPlate matches rating, group, impedance and serial
Type tests, design verification
Temperature riseWinding and oil under load
Lightning impulseWithstand against surge
Short circuit withstandMechanical and thermal
Diagnostic, on request
Dissolved gas analysisOil condition and fault gases
Partial dischargeInsulation weakness
Frequency responseWinding displacement
The rating plate03 / 04

The last test is the plate itself

Every transformer Transfix builds carries a rating plate: stamped, tabular and entirely factual. No decoration, no persuasion, just the numbers a buyer needs in the order they need them.

Rating plate verification is a routine test on every unit. The plate is checked against the build for rating, vector group, impedance and serial number before the unit is released.

A Transfix technician running routine production tests in the test bay at Botshabelo
Rated power
315 kVA
HV / LV
22 kV / 420 V
Phases
3
Cooling
ONAN
Standard
SANS 780
Serial
TX-000000
Commitment04 / 04

What we hold ourselves to

TO REMAIN

A company that contributes actively to B-BBEE, and that supplies the South African market with three phase distribution transformers known for consistent quality, industrial skill and responsive customer care.

TO SUCCEED

Through employees who grow in competence, work to clear goals and deliver on what they set out to do, in partnership with suppliers who share our demand for progress.

TO LEAD

An environmentally responsible operation, compliant with all applicable legislation, that protects the safety of our personnel and of the general public.

Test certificates

Ask us for a sample certificate

We will send you the routine test certificate format so you can see exactly what is issued with every unit before you order.

Get in touch