On Wednesday morning, Eskom group CEO André de Ruyter admitted to Parliament that a recent fire at unit 5 of the Kusile Power Station may delay the unit’s completion by a whole year, until December 2024. A month ago, a fire broke out at a gas air heater at unit 5, which is being commissioned and has not yet been synchronised to the grid.
News
You are here: Home1 / News2 / Industry News3 / Kusile fire may delay completion of 800 MW unit by a year, warns De Ru...
You might also like
INDUSTRY NEWS
WHERE TO FIND US
Address
9 Yellow Street
Botshabelo Industrial Area
Botshabelo, Free State
Call / Email Us
Tel: +27 (0) 61 956 6772
Email: info@transfix.co.za
SOME OF OUR PRODUCTS
CALENDAR
M | T | W | T | F | S | S |
---|---|---|---|---|---|---|
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |