Renewable energy company G7 has failed to interdict Eskom from applying its new grid access rules. Had the interdict been granted, the progress of new energy projects, both those planned by the private sector and those commissioned to supply Eskom, would have stalled. Judge Basheer Vally dismissed the application for an interdict, with costs, on Monday. Part B of the case – on the substantive issue of Eskom’s authority to change grid rules – is still to be argued.
You might also like
INDUSTRY NEWS
- AfDB approves $10m loan to support Hyphen’s Namibian green ammonia projectDecember 10, 2025 - 4:04 pm
- Merafong becomes third municipality to sign electricity distribution agreement with EskomDecember 10, 2025 - 2:04 pm
- NTCSA outlines envisaged role for new TSO sans grid assetsDecember 10, 2025 - 11:04 am
WHERE TO FIND US
Address
9 Yellow Street
Botshabelo Industrial Area
Botshabelo, Free State
Call / Email Us
Tel: +27 (0) 61 956 6772
Email: info@transfix.co.za
