Renewable energy company G7 has failed to interdict Eskom from applying its new grid access rules. Had the interdict been granted, the progress of new energy projects, both those planned by the private sector and those commissioned to supply Eskom, would have stalled. Judge Basheer Vally dismissed the application for an interdict, with costs, on Monday. Part B of the case – on the substantive issue of Eskom’s authority to change grid rules – is still to be argued.