State-owned utility Eskom has been ordered by a high court to pay more than R1-billion to French nuclear energy company Framatome, after contract and project management problems delayed a steam generator swap at the entity’s Koeberg nuclear power plant, newspaper Business Day reports. In an article on July 21, reporter Kabelo Khumalo reports that the adjudication process, which was handled by advocate Peter Ramsden, resulted in the court ordering Eskom to pay Framatome €35.2-million (R727-million) and a further R256.6-million, in line with Ramsden’s earlier findings.