Eskom Holdings =has imposed conditions to access the national grid on 1 850 MW worth of projects in South Africa that developers including Karpowership and Electricite de France SA have struggled to complete since they were awarded in March 2021. The right to access the grid is “conditional based on the projects achieving certain milestones by December 2023,” Eskom said on Wednesday in a response to queries. “This is in line with Eskom’s objective to have projects connect to the grid as soon as possible and to discourage capacity hogging.”