After several delays since its launch in 2017, the $294-million Kariba Dam Rehabilitation Project (KDRP), aimed at repairing decades of erosion from high-velocity water discharge and refurbishing the dam’s spillway, is now largely complete, with remaining works due to wrap up by September next year. The project’s core components are the reshaping of the dam’s plunge pool, completed in September last year, and the refurbishment of all six sluices in the spillway, the first phase of which is now 99% complete, with finalisation expected before year-end. Phase II, which began in 2024, has progressed to the 26% completion mark, with overall works scheduled to conclude in just under a year.