Eskom says that the main mechanical work on replacing the steam generators at Koeberg’s Unit 1 has been completed and it will return to service on 3 November. Koeberg’s Unit 2 will be taken offline on 7 November, slightly later than anticipated two weeks ago, avoiding the problem that both units would be offline simultaneously.
News
You are here: Home1 / News2 / Industry News3 / Koeberg Unit 1 on track to return to service in early November
You might also like
INDUSTRY NEWS
WHERE TO FIND US
Address
9 Yellow Street
Botshabelo Industrial Area
Botshabelo, Free State
Call / Email Us
Tel: +27 (0) 51 534 1651
Email: info@transfix.co.za