Eskom says that the main mechanical work on replacing the steam generators at Koeberg’s Unit 1 has been completed and it will return to service on 3 November. Koeberg’s Unit 2 will be taken offline on 7 November, slightly later than anticipated two weeks ago, avoiding the problem that both units would be offline simultaneously.