Power utility Eskom will implement Stage 5 loadshedding from 16:00 this afternoon until 05:00 on Friday. Thereafter, various stages of loadshedding will be implemented over the weekend. Breakdowns have decreased to 16 369 MW of generating capacity, while the generating capacity out of service for planned maintenance is 3 369 MW.