The associations representing the wind and solar sectors as well as independent power producers (IPPs) more generally are eagerly awaiting a proposed curtailment addendum to Eskom’s Grid Connection Capacity Assessment (GCCA), which is published yearly to provide connection visibility for new utility scale generators. The latest GCCA was published at the end of October and states that, while there is still 19.9 GW of capacity available, all capacity has been absorbed in the Eastern, Western and Northern Cape provinces, as well as Eskom’s Hydra Central grid area, which borders the Cape provinces and the Free State.