The Department of Mineral Resources and Energy (DMRE) has provided an updated timetable for the implementation of its long-term electricity procurement programmes, which are being pursued in line with a Section 34 Ministerial determination, published in September 2020, and catering for the procurement of more than 11 800 MW of new generation and energy storage capacity. Following a seven-year interruption, the Renewable Energy Independent Power Producer Procurement Programme (REIPPPP) resumed in April with the release of a request for proposals (RFP) for bid window five (BW5), through which government is seeking to procure 2 600 MW of new solar photovoltaic (PV) and wind capacity.