Eskom told lawmakers on Wednesday that a fire in the gas air heater of Kusile Unit 5, which occurred during a commissioning exercise on September 17, represented a major “setback” and could delay the 800 MW unit’s entry into commercial operation by up to a year. Under the revised scheduled for the much-delayed Kusile build programme, Unit 5 was expected to enter into commercial operation in December 2023.
News
You are here: Home1 / News2 / Industry News3 / Gas air heater fire could delay commercial operation at Kusile Unit 5 by...
You might also like
INDUSTRY NEWS
- Germany reaffirms €2.68bn commitment to South Africa’s Just Energy TransitionJanuary 23, 2026 - 5:04 pm
- Nersa activates electricity tribunal powers, issues default orders against five municipalitiesJanuary 23, 2026 - 4:04 pm
- Great progress made on operational stability – utilityJanuary 23, 2026 - 1:04 am
WHERE TO FIND US
Address
9 Yellow Street
Botshabelo Industrial Area
Botshabelo, Free State
Call / Email Us
Tel: +27 (0) 61 956 6772
Email: info@transfix.co.za