Eskom told lawmakers on Wednesday that a fire in the gas air heater of Kusile Unit 5, which occurred during a commissioning exercise on September 17, represented a major “setback” and could delay the 800 MW unit’s entry into commercial operation by up to a year. Under the revised scheduled for the much-delayed Kusile build programme, Unit 5 was expected to enter into commercial operation in December 2023.
News
You are here: Home1 / News2 / Industry News3 / Gas air heater fire could delay commercial operation at Kusile Unit 5 by...
You might also like
INDUSTRY NEWS
WHERE TO FIND US
Address
9 Yellow Street
Botshabelo Industrial Area
Botshabelo, Free State
Call / Email Us
Tel: +27 (0) 51 534 1651
Email: info@transfix.co.za
SOME OF OUR PRODUCTS
CALENDAR
| M | T | W | T | F | S | S |
|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | |||
| 5 | 6 | 7 | 8 | 9 | 10 | 11 |
| 12 | 13 | 14 | 15 | 16 | 17 | 18 |
| 19 | 20 | 21 | 22 | 23 | 24 | 25 |
| 26 | 27 | 28 | 29 | 30 | 31 | |
